Public Works Projects For the Week of
July 26-30, 2010

This list is arranged in the order by affect on
traffic. Those at the top of the list
are MOST likely to impact traffic.

2010 Chipseal Program
The City will be working in the following areas next week:

Monday, July 26—chipsealing at the following locations:

  • Mulberry Street from Highway 340 to I-70B
  • Gunnison Ave. from Crosby Ave. to Mulberry St.
  • Maldonado St. from W. Ouray Ave. to Gunnison Ave. and the cul-de-sac
  • Peach St. from Gunnison Avenue to end of pavement

Tuesday, July 27—chipsealing at the following locations:

  • Martello Dr. from S. Redlands Rd. to the cul-de-sac near Martello Dr.
  • Snowmass Court, Antero Ct., Rodell Dr., Pikes Peak Dr., Mount Sporis Dr., E. Mayfield Dr., W. Mayfield Dr., W. Mayfield Ct., Willow Ridge Ct., High Pointe Dr., High Pointe Circle.

Wednesday, July 28--Chipsealing in the following locations:

  • Dressel Dr., Ridge Circle Dr., Valley View Way, School Ridge Rd., Hill View Dr., and Rattlesnake Court.

Thursday, July 29—chipsealing in the following locations:

  • W. Valley Circle, Ridge View Dr., Rana Rd., Butte Court, Prospectors Point, Saddle Court, Eagle Crest Court, and Ridgeway Court.

The public is cautioned that oil and chips will be placed on the road surface during this process. Please drive slowly through the work zone to avoid damage to your car or windshield.

CDOT Widening of I-70B
This project will widen I-70B between 24 Road and 24 ¾ Road. Traffic has been switched to the south side in the construction zone and will remain that way through the end of September.

2010 Waterline Replacement Project—Phase 1
Night work will continue to tie waterline services to the new line. Expect lane closures from 7 PM to 8 AM on North Ave. from 6th Street to 11th Street. 

2010 Waterline Replacement Project—Phase 2
Patterson Road: Waterline work continues in Patterson Road starting at 27 ½ Road and working west to 7th Street. Within the construction zone, all traffic on both sides of that zone will be narrowed to one lane.  On Monday, daytime work will begin on boring a new waterline underneath the irrigation canal just east of St. Mary’s Hospital on Patterson. Night time work will include testing the mains, installing lateral lines and reconnecting services a section at a time. Waterline work will continue until late July.

2010 Waterline Replacement Project—Phase 3
Crews are working in 28 ½ Road starting at Elm and proceeding to North Avenue

29 Road Overpass

  • Construction is underway on the 29 Road overpass over the Union Pacific railroad tracks and I-70 B.
  • 29 Road from I-70B north to Teller is closed permanently.
  • Pile driving will take place near I-70B with lane closures in the eastbound lane.
  • Sewer line work will be taking place on the frontage road near 29 Road with flaggers in place to direct traffic.
  • The westbound shoulder on the frontage road will be closed in the construction zone.
  • Speed limit in the construction zone is 40 mph. Fines are doubled in the work zone.  

D Road Bridge Replacement
D Road is closed to through traffic from the intersection southeast of Monument Road to the south for the replacement of the bridge that crosses No Thoroughfare Wash. Residents and visitors to the Rosevale area will be directed to use South Redlands Road as the detour. Please slow down on this detour—South Redlands Road is narrow, steep, and has several blind curves. The detour is on a school bus route and is also used by pedestrians and bicycle riders. Slow down and share the road. The project will be completed by August 19.

2010 Parkway Sanitary Sewer Interceptor Project
Work continues on construction of a new sewer from the intersection of 15th Street and Winters Ave. south to the Parkway and then west along Struthers Ave. to just west of 5th Street. The west end of Struthers is currently closed to traffic. Access to Elam, Randall Industries, B&H Construction and the Botanical Gardens is still open, and may be accessed via 7th Street to Struthers. The project will be completed in July.

30 Road/Eastmoor Sewer Line Replacement Project

  • Central Grand Valley Sanitation District (CGVSD) will be replacing the existing sewer line in East Vista Drive, Ronlin Drive, F Road, 30 Road, Bookcliff Avenue (East of 30 Road), Green Place, Green Court, Eastmoor Drive and Pearwood Court.  The project is expected to be complete by November 2010. The original concrete sewer pipe, which is deteriorating, will be replaced with a PVC line.  
  • Work hours on 30 Road and F Road will be from 8:30 a.m. to 4:00 Monday through Friday.  The intersection of 30 Road and F Road will be completed during the night, from 7:00 p.m. to 6:00 a.m. because of the extent of the work and the safety of the contractor and the general public.  The work hours for the other sections of the project will be from 7:00 a.m. to 6:00 p.m. Monday through Friday and weekends when necessary.  
  • There will be road closures and detours on residential streets when construction is immediately in front of those areas.  The speed limit will be reduced to 30 mph in the immediate work area.  Double fines will be enforced for speeding in the construction zone. 

32 ½ Road Closure
32 ½ Road will be closed from E ½ Road north to Front Street from July 12 through August 30. Grand Valley Drainage District is installing a Mesa County storm drain line. Access will be from 32 5/8 Road.


Traffic Volume Cams

The Communications and Community Relations Coordinator manages the City’s overall communications activities, disseminates information to the media and the public, produces video programming, and publishes the City’s newsletter and annual calendar.

Subscribe to the Public Works Projects via e-mail. You will automatically receive an e-mail notification when new content is published.

You may unsubscribe at any time.

This page updated
Friday, July 23, 2010

 

This site requires Adobe Acrobat Reader

 
  City CouncilFire DepartmentJob OpportunitiesNews ReleasesParks and RecreationPoliceVisitor and Convention Bureau  
  City of Grand Junction, Colorado  Copyright 2001DisclaimerEmail the Webmaster